migamildien Wrote:
-------------------------------------------------------
> the question doesnt give a current point in time
> to use as the TODAY marker in the gantt and slip
> charts. so how do we do this? and how do we
> display progress? must we do 4 gantt and slip
> charts to display progress at each point in time
> given?
start at any point in time. Remember that weeks are working weeks, i.e. 5 days. Divide the project into phases - that's what it means anyway. Eg: planning phase of 17 days is the first horizontal bar. The next group starts where the first ends, and so on.