for this question:
Anna – Analyse existing systems (2 weeks)
Bennie – Obtain user requirements (3 weeks
Connie – Plan office layout (3, 5 weeks)
Pieter – Issue tender (4, 5 weeks)
(Note: the weeks in brackets denote the scheduled time within which the project is to be completed.)
is it correct to interpret it as:
Anna week 1 -> week 2
Bennie week 1 -> week 3
Connie week 3 -> week 5
Pieter week 4 -> week 5
in other words pieter start work at week 4 and plans to complete at week 5?