I think that we have to rethink activity 2, 3 and 4 so here goes.
(That is in terms of the latest dates.
activity 4 (only one option)
> 24 - 10 = 14
activity 3
> 14 - 7 = 7 <--- this is what the assignment result was
> 32 - 16 = 16
activity 2
> 24 - 9 = 15
> 14 - 6 = 8 <--- this is what I think it must be ***
*** in light of what morgoth said in the previous message it cannot be 15 because then it would miss the latest possible date for activity 4 ! ! !
That is 15 + 6 = 21 days - and the latest date that activity 4 can be completed in is 14 days!!!!
Take a look at this description I have given above and let me know if you also go for the earliest end date of 8 or if we should always take the latest of 15???
If so then activity 3 is incorrect!!!! since 16 is the latest date possible - opposed to 7 !?!?
please make sense of this,
cheers