May 22, 2006 09:13AM
I cannot understand how the latest end date of a event is obtained. I have looked at the diagrams but cannot figure it out. Can anyone help me?
Re: Arrow-on-activity
May 27, 2006 07:16AM
Take the latest date from the event that the acitivity is directed to and subtract the duration of the event and that will be your result. For instance, event B:
The latest date from event 4 is 11 hence the latest date for event 3 will be 11 minus the duration of activity D whichi is 4, the result 7 is depicted in event 3.

I hope this helps.
Thanks
Yousuf